Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

rebaseline

6 replies [Last post]
Forum Guest
User offline. Last seen 18 weeks 3 days ago. Offline
Joined: 28 Jan 2009
Posts: 2
Groups: None

how does primavera rebaseline when tracking project

i want to understand how p3 resolve the problem of new BQWS with the BQWP

you know that when you want to re-baseline a project
you must to put BQWS=BQWP

i want to know how p3 do that

is it with " GLOBAL CHANGE" or something else

i’m here for more explications

thank for your help

Replies

Zq qz
User offline. Last seen 12 years 46 weeks ago. Offline
Joined: 6 Jun 2003
Posts: 163
Groups: None
Another method is using your current schedule as your target
Bensouyah Mohamed
User offline. Last seen 16 years 37 weeks ago. Offline
Joined: 7 Jan 2004
Posts: 7
next time i’ll give u a real example of project
MK TSE
User offline. Last seen 4 years 25 weeks ago. Offline
Joined: 27 Feb 2002
Posts: 550
Groups: None
Make use fields, like custom data fields, to store some calculated values in step by step calculation.
The whole process is control by global change.
Zq qz
User offline. Last seen 12 years 46 weeks ago. Offline
Joined: 6 Jun 2003
Posts: 163
Groups: None
Another method is Update Target Option
Forum Guest
User offline. Last seen 18 weeks 3 days ago. Offline
Joined: 28 Jan 2009
Posts: 2
Groups: None
please more explications
MK TSE
User offline. Last seen 4 years 25 weeks ago. Offline
Joined: 27 Feb 2002
Posts: 550
Groups: None
by global change to update the required field(s).