Re-baselining

2 replies [Last post]
Rahmat Hidayat
User offline. Last seen 51 weeks 18 hours ago. Offline
Joined: 30 Jul 2002
Posts: 82
I want to do re-baselining while my project has been in progress but I want to keep the historical ACWP curve and its ETC curve as new baseline for each activities. How to do it in P3 ?

Thks

Replies

MK TSE
User offline. Last seen 4 years 17 weeks ago. Offline
Joined: 27 Feb 2002
Posts: 550
Groups: None
Create a copy of your baseline. Carry out the re-baseline works on the copy.
Luca Basile
User offline. Last seen 9 years 33 weeks ago. Offline
Joined: 10 Jul 2003
Posts: 288
Groups: TILOS
I am used to make the S-curve in excel as I had problem with the store period performance.
So If You have to re-schedule a new baseline, I suppose a new completion data was agreed or You have to recover some delays. Good You just re-schedule the outstnd work and keep the done.
As It can help You to have stored in a ufficial docs the project hystorical info.
And then the same.

The problem with store period performance is:
If I do not use it P3 spreeding the performance achieved on the past, so if I have an activity started from 2 progress time (let say weeks) anmd 10 ut earned the first week and 40 the second on, P3 spreed 25 ut between the two weeks.
Using store period performance in huge shcedule time by time I have strange error message.