Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Total Float Bar on Completed Activities

2 replies [Last post]
Utku Çil
User offline. Last seen 10 years 7 weeks ago. Offline
Joined: 7 Jun 2011
Posts: 29

Is there a way that I can remove the total float bar on completed activites?

I have an on-going schedule having completed, in progress & not started activities as can be predicted but I want to see the total float bar only for in progress & not started activities since, in my opinion, total float does not mean anything for completed activites.

Thanks in advance for who replies..

Replies

Utku Çil
User offline. Last seen 10 years 7 weeks ago. Offline
Joined: 7 Jun 2011
Posts: 29

Thank you Gary,

It seems to be really simple as I guessed :)

Gary Whitehead
User offline. Last seen 5 years 25 weeks ago. Offline

See extract from a Paul Harris presentation covering this:

 

675
completed_float.jpg