displaying total float for completed activities!!

6 replies [Last post]
Amir Dadbakhsh
User offline. Last seen 3 years 35 weeks ago. Offline
Joined: 13 Oct 2004
Posts: 42
Hi guys,
In my time schedule, primavera shows total float>0 for completed activities instead of zero (0) !!!
if anyone has same experience and could solve this bug, please put his/her solution here
thanks in advance
amir

Replies

Ronald Winter
User offline. Last seen 3 years 18 weeks ago. Offline
Joined: 4 Jan 2003
Posts: 928
Groups: None
This is actually not a ‘bug,’ just a perceived one. Starting with Version 5, Primavera stopped deleting the early and late dates stored in the database for actual activities It comes as a surprise to everyone but the software industry that completed activities also have ‘float.’

What Primavera forgot to do in their P5 release was to blank out the float column for completed activities. This caused quite a stir in the Users’ World as they were not used to seeing completed activities with float. Very soon after the release of P5, Primavera released Service Pack 1 that corrected this ‘error’ by not printing the float for completed activities. The values still exist in the database, they just are not shown anymore using SP1.
Marcio Sampaio
User offline. Last seen 11 years 46 weeks ago. Offline
Joined: 7 Nov 2005
Posts: 658
Hello all,

Is SP2 for P5 solving this bug?

Regards.

Marcio Eduardo.
David Kelly
User offline. Last seen 1 year 50 weeks ago. Offline
Joined: 19 Oct 2004
Posts: 630
OOPS - I have not made clear that it is "retained logic" that exhibits this problem "progress override" and "actual dates" do not.
David Kelly
User offline. Last seen 1 year 50 weeks ago. Offline
Joined: 19 Oct 2004
Posts: 630
its a known "bug". If you schedule using "progress override" or "actual dates" rather than "retained logic" - you find these selections under scheduling options. PO and AD do dreadfull things to your schedule if you have out-of-sequence progress - but thats the only issue.
Amir Dadbakhsh
User offline. Last seen 3 years 35 weeks ago. Offline
Joined: 13 Oct 2004
Posts: 42
I forgot to say that i use primavera v5
Amir Dadbakhsh
User offline. Last seen 3 years 35 weeks ago. Offline
Joined: 13 Oct 2004
Posts: 42
David,
Thanks a lot