Data Export

4 replies [Last post]
Forum Guest
User offline. Last seen 18 weeks 3 days ago. Offline
Joined: 28 Jan 2009
Posts: 2
Groups: None
Please could anybody tell me if it is possible to export individual project data dates from a Project Group?
I have tried using the report writer in the Project group but it specifies the Group data date only for all Sub-Projects. Any Ideas???
I am trying to create a Group report which identifies when a sub -project was last updated.

Replies

Forum Guest
User offline. Last seen 18 weeks 3 days ago. Offline
Joined: 28 Jan 2009
Posts: 2
Groups: None
Thanks Jorge

What you`ve said will suffice for my purpose although I was hoping for a simpler report.
I can still utilise excel to give me what i need in the way of a simple report.
Jorge Taguinod
User offline. Last seen 2 years 50 weeks ago. Offline
Joined: 8 Jul 2003
Posts: 139
Hi Forum Guest,

1. First, make sure that your setting allows for multiple project data dates.

From the menu, select: >Tools >Schedule> Options
Select Advanced Tab
Remove check from "Project Group Scheduling"

2. Run the schedule with the Schedule Statistics Report.
From the menu, select: >Tools >Schedule >Schedule Now.
Note: Do not use F9 as this doesnt bring out the Report.

You will see in the report that the different projects in the project group will have different project start dates, project finish dates, data dates, etc.

Hope this helps.

Best regards,

Jorge
MK TSE
User offline. Last seen 4 years 25 weeks ago. Offline
Joined: 27 Feb 2002
Posts: 550
Groups: None
In option, uncheck overwrite sub-project data date when scheduling.
Steven Oliver
User offline. Last seen 12 years 1 week ago. Offline
Joined: 8 Nov 2002
Posts: 313
Groups: None
How about creating a Custom Data Item (type = start) in each of the subprojects use a global change to set the value of the CDI = Data Date.

Bit long winded but it works. If I remember right you can also use PRMBatch, but I dont have the manual (or the CD).