Resource Spreading Primavera

2 replies [Last post]
Jithin Kambhikanam
User offline. Last seen 5 weeks 4 days ago. Offline

Hi All,

I have an activity in Primavera with a duration of 15 Days but I need the resource till 10 the Day

Is there a way to spread the budgeted resource to only the 10th Day ?

 

Thansk

Jithin 

Replies

david kelly
User offline. Last seen 1 day 24 min ago. Offline
Joined: 12 Feb 2016
Posts: 35
Groups: None

Jithin,

 

Yes there is. The resource assignment record has fields which you can see in the Activity Details forms, for Resource lag (how long after the activity starts the resource is required, and resource duration.

BUT you have to be very careful with the Project Level 'Drive activity dates by default' switch, if a resource (e.g. 'Get Paid') is not within the sceduled start and finish date of the activity. Your example of (I think) a resource required for the first 10 of fifteen days will not change the activity duration

david kelly
User offline. Last seen 1 day 24 min ago. Offline
Joined: 12 Feb 2016
Posts: 35
Groups: None

Jithin,

 

Yes there is. The resource assignment record has fields which you can see in the Activity Details forms, for Resource lag (how long after the activity starts the resource is required, and resource duration.

BUT you have to be very careful with the Project Level 'Drive activity dates by default' switch, if a resource (e.g. 'Get Paid') is not within the sceduled start and finish date of the activity. Your example of (I think) a resource required for the first 10 of fifteen days will not change the activity duration