It feels as though I have learnt 2 years of planning skills in 2 days reading through these forums, so I thought I would try my luck with another query.
In resource assignments I am trying to ascertain % complete instead of units using resource assignments. for example I currently have a bulk ew material resource, the resource assignment then allows me to see how many units (bcm) will be expended over time however I want to see % of remaining. I am currently using excel to do the spreading. I am expecting something like the top table, instead of the qtys on the bottom. Mind you it is not hard to do in excel but would be nice to use P6 instead
Activity |
30-Apr-12 |
7-May-12 |
14-May-12 |
21-May-12 |
28-May-12 |
4-Jun-12 |
11-Jun-12 |
18-Jun-12 |
25-Jun-12 |
2-Jul-12 |
9-Jul-12 |
GLNG 651 (Day/Night) |
1.95% |
1.91% |
1.82% |
2.53% |
2.53% |
1.66% |
1.89% |
1.98% |
1.55% |
1.56% |
1.38% |
|
|
|
|
|
|
|
|
|
|
|
|
Activity |
30-Apr-12 |
7-May-12 |
14-May-12 |
21-May-12 |
28-May-12 |
4-Jun-12 |
11-Jun-12 |
18-Jun-12 |
25-Jun-12 |
2-Jul-12 |
9-Jul-12 |
GLNG 651 (Day/Night) |
28800 |
36000 |
33300 |
43200 |
47634 |
30600 |
36000 |
43200 |
43200 |
43200 |
43200 |