Interpretation of Progress S-Curve without Schedule
Case-1 the actual overall actual progress value of reporting period is less than the overall early planned value but above the overall late planned value: the agreed baseline completion of Project may or may not get extended, all depends on the progress achieved on the planned critical path.
Case-2 the overall actual value reported is below the overall late planned value: does it mean that the agreed Project completion date is extended, or it depends on the progress on the critical path
Appreciate your kind thoughts....
Kannan