Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

P6 Programme Update Issue

1 reply [Last post]
R L
User offline. Last seen 5 years 23 weeks ago. Offline
Joined: 14 Jun 2019
Posts: 2
Groups: None

Hi All,

I have a latest programme update (monthly) in hand with project completion in June. It is anticipated that extension of time of 3 months to the project would be expected, but due to administration process its unlikely to be awarded anytime soon.

At the same time, I need to issue a variation order which is very much independent to the on-going works, and was requested to show that it has no time impact to the project completion. Issuance of such variation (say 4 weeks duration) would be later than the current project completion date, but comparing to the anticipated project completion date, it would undoubtedly have 2 months of float. Now my problem is when insert the activity into the programme and schedule it, it would become out of sequence logic and the float would be negative and activity bar in red because completion has yet to be extended. Could anyone advise how would you go about presenting such analysis to your client/superior?

Your advise is appreciated. Some sample or screen cap would be great. Thanks.

R

Replies

Zoltan Palffy
User offline. Last seen 3 weeks 23 hours ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

Thats not true out of sequence logic happens when you start an activity before its predecessor has completed.

Since this is a new activity all you are doing is inserting it and it has nothing to do with out of sequence

out of sequence example

install conduit finish to start relationship tp pulling wire

as you progress the schedule you have started conduit but you are not 100 % complete but you have started pulling wire

this is out of sequence progress

I do not know what out of sequence logic is 

it depends on where you insert this new activity as to if it pushes out the end date or not meaning where you assign it predcessor and its successor.