P6 Actual Cost

1 reply [Last post]
Maxim Dr
User offline. Last seen 5 years 25 weeks ago. Offline
Joined: 25 Jul 2017
Posts: 6
Groups: None

Hello,

In my P6 current settings, the actual cost is calculated as Total Units * Rate. The total units are collected from the period units. Is there a way to collect the actual cost from the Period Actual Cost? Say, the actual cost in Jan is 100$, Feb - 150$, I want to see 250$ in the Actual Total Cost, regardless of what units are? What settings do I need to change?

If this question has already been discussed, please refer me to the relevant thread.

Thank you very much.

Replies

Zoltan Palffy
User offline. Last seen 20 weeks 3 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

make sure that 1st you set up your periods. To do this go to the Admin then Financial Periods and set up your periods.

 

then after each update select tools store period performance