Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Resources and Hammock activity

6 replies [Last post]
Ahmet Tuter
User offline. Last seen 3 years 27 weeks ago. Offline
Joined: 7 Feb 2013
Posts: 52
Groups: None

Can we assign resources to Hammock activity?

Also is this same as a summary activity?

Replies

Rafael Davila
User offline. Last seen 2 weeks 2 days ago. Offline
Joined: 1 Mar 2004
Posts: 5241

Hi Patrick,

very good article, thank you.

We also use hammocks to summarize resource idle time using variable resource assignment. In this case resource hours are assigned to hammocks when they are not used on other project activities. But I don't know other tools except Spider Project that model variable resource assignments.

Patrick Weaver
User offline. Last seen 5 days 6 hours ago. Offline
Joined: 18 Jan 2001
Posts: 383
Groups: None

Hammock and summary activities are quite different in concept (although many software developers confuse them).  The primary purpose of a true 'hammock' is to carry resources required for a period of time dictated by other activities in the schedule! For more on this see: https://mosaicprojects.com.au/Mag_Articles/P016_Hammocks_LOE_and_Summary_Activities.pdf

Zoltan Palffy
User offline. Last seen 3 weeks 6 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

yes in p6 you can

when you say summary activity what exactly do you mena do you mean a WBS summary activity  ?

a hammock activity grows and shrinks with the activities that it is summarizing. 

a hammoack activity can summarize any type of acivities across multiple wbs's for excample lets say you wante dto summarize all of the concrete activities. The you would create a hammock activity that has a predecessr with a start to start relationship to the 1st concrete activity and would have a successor with a finish to finish realtionship to the last concrete activity. The hammock activity would span this time frame. 

You can not do this with a wbs summary or with a summary type bar so the answer is yes they are different. 

Mike Testro
User offline. Last seen 21 hours 52 min ago. Offline
Joined: 14 Dec 2005
Posts: 4420

In Asta Powerproject you cannot assign anything to a hammock or link to it but you can put a summary bar over it and use that.

But links to and from a summary bar over a hammock behave in the opposite to ASAP and ALAP.

Weird.

I expect that it depends on the software that is used.

In Spider Project resources can be assigned to hammock activities and hammocks participate in resource leveling.

I am not sure that the same is applicable to other tools.