Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Hammock Activity

3 replies [Last post]
John Herry
User offline. Last seen 3 years 25 weeks ago. Offline
Joined: 14 Feb 2007
Posts: 2
Dear all,

I would like to know about:

1. What is the Hammock Activity?
2. Why and when do we have to analyze the Hammock Act.?

Thanks in advance.

Warm Regards,
Tenten


Replies

Muhammad Jawad Sh...
User offline. Last seen 13 years 14 weeks ago. Offline
Joined: 21 Oct 2007
Posts: 9
Groups: None
Please note the following,
Hammock activity has nothing to do with the program of works or Time Management. Its main purpose is cost and resource loading.
Just filter them and save them in a separate layout.
Take Care
Muhammad Jawad
A D
User offline. Last seen 4 years 2 weeks ago. Offline
Joined: 20 May 2007
Posts: 1027
Refer the link below, thread already discussed a lot of time:

http://www.planningplanet.com/forum/forum_post.asp?fid=1&Cat=2&Top=34543

Cheers,

Raviraj A Bhedase
kartik rao
User offline. Last seen 13 years 9 weeks ago. Offline
Joined: 23 Nov 2003
Posts: 5
Groups: None
Tenten,

A hammock activity is one that summarizes the duration of a set of activities. It is not the total duration of the set of activities but the duration between the start of the earliest and the end of the latest activity.

It is tool to monitor a set of activities eg. if you have 5 activities that have progressed differently on updating , the hammock can give you a realistic percentage completion figure.

In some cases, i have seen programmes with hammocks loaded with resources for ease of allocation and reporting.

The one issue that you will have to consider is that a hammock activity is not a real activity, its just an indicative activity. but in certain updated programme, the hammock might end up sitting on the critical path. It is important to ignore the hammock activities at that stage.

hope this clarifies