Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

XER file at completion units is changed.

1 reply [Last post]
AEJAZ AHMED AHMED
User offline. Last seen 7 years 31 weeks ago. Offline
Joined: 6 Apr 2014
Posts: 7
Groups: None

Dear Friends

whenver i importing XER file at completion units is changed.

we are using server based software. means we are updating the programme multiple users.

and we are using unit percentage complete.

so please help...

Replies

Zoltan Palffy
User offline. Last seen 3 weeks 1 day ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

what is your Resource assigment setting in the Projects directory ?

add actual to remaining or subtract actual from at completion ?

also do you have Recalculate Actual Units and costs when duration % changes ?