san TS
User offline. Last seen 3 years 47 weeks ago. Offline
Joined: 12 Dec 2011
Posts: 19
Groups: None

Hi,

I exported a schedule including the baseline into XER file.Then when i restore ,the early start and early fiish dates are ok,but the BL start and BL finish are not same as the original file.What could be the reason??

 

Best Regards,

 

San

Replies

san TS
User offline. Last seen 3 years 47 weeks ago. Offline
Joined: 12 Dec 2011
Posts: 19
Groups: None

Ronald,

Even when you assign a baseline and export it to .XER file, when you import and then open , you could see that baseline column shows the dates of early start and early finish and not the actual baseline dates, which implies that the baseline is not getting exported into the .XER file.

So when you make a schedule update and preserve it in .XER file, the baseline doesn't follow that file.So you have to save the original baseline and re assign it to the schedule update each time you update the schedule.

Please let me know if there is a better option

 

Best Regards,

San

san TS
User offline. Last seen 3 years 47 weeks ago. Offline
Joined: 12 Dec 2011
Posts: 19
Groups: None

You are right SM, baseline doesn't get exported.

Thanks

BR,

San

Ronald Winter
User offline. Last seen 3 years 23 weeks ago. Offline
Joined: 4 Jan 2003
Posts: 928
Groups: None

San,

You always have baseline dates, even when no baseline is assigned.  When no baseline is assigned, your current Planned Dates are displayed as the baseline dates.  This is probably why you think that they have ‘changed.’  The baseline dates did not change, the baseline probably did not transfer or it is no longer assigned.  Good luck!

SM PUM
User offline. Last seen 10 years 26 weeks ago. Offline
Joined: 15 Nov 2011
Posts: 77
Groups: None

san TS

When you export .XER file then Baseline is not exported.You hace to Restore it.

 