Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Activity % Complete

2 replies [Last post]
TUNJI ADEWALE
User offline. Last seen 4 years 48 weeks ago. Offline
Joined: 18 Jul 2014
Posts: 13

Hi Members,

Can anybody help me with updating activity % complete from importing excel file. I am currently facing issues in this. I can and have been able to export my p6 file to excel, update and re-import and its all working fine for BudgetedTotal Cost, Budgeted Unit, Duration and so on. But for Activity % Complete, it is not working?

 

Pls Help

Replies

Dieter Wambach
User offline. Last seen 7 years 28 weeks ago. Offline
Joined: 15 Jan 2007
Posts: 1350

Hi Yakubu

There are two conditions to maintain this item manually:

1. The activity must be started, as Jerome wrote

2. Percent complete type must be physical. For the two other types (duration, units) it is always calculated by P6.

Regards

Dieter

Jerome Odeh
User offline. Last seen 9 weeks 7 hours ago. Offline
Joined: 19 Jan 2004
Posts: 102

Hi Yakubu,

You also need to update Actual Start Date for the updated Activity % Complete to be reflected.

 

=jerome