Activity % Complete in Totals and Sub-totals do not appear

6 replies [Last post]
arvin pura
User offline. Last seen 9 years 27 weeks ago. Offline
Joined: 17 Mar 2014
Posts: 8

Hi Planning Experts,

Currently I am updating my programme in P6. My programme is resource loaded with manpower and material. In updating I am using Activity % complete in the column and physical % as the percent type. But after updating there I cannot see the % complete in the total and subtotals (or wbs bars). Need help and advise.

 

Thank you.

Arvin

Replies

Rangarajan Ramaswamy
User offline. Last seen 1 year 51 weeks ago. Offline
Joined: 1 Dec 2009
Posts: 24

Hey Arvin , i got your problem. Understand one thing P6 never shows summary % complete in Activity % column. Chew on it. To know % progress at summary level you have to add Performance % Complete column.

Now switch to P6 and do that first before you continue.

 

Voila!! there you go, now you can see the % complete and can thank me for that.

 

However if P6 still doesnt show the % complete at sumary level follow the below steps.

I want you to check if you have assigned cost for your resources.

If not, P6 is not going to give you a damn % complete on Summary level.

So you have two options:-

1. If you do not want your schedule to be cost loaded, just put resource Price/unit as 1/unit. Recalculate assignment cost. This will get you going. Or

2. Load the actual cost of resources and materials, you have the % complete in summary bars.

I hope this solves your problem.

Regards,

Ranga

Gary Whitehead
User offline. Last seen 5 years 15 weeks ago. Offline

Arvin,

 

It works for me, so not sure what to advise. -Have you baselined?

Kannan CP
User offline. Last seen 9 weeks 5 days ago. Offline
Joined: 12 Jun 2008
Posts: 290
Groups: None

Hi Arvin,

Activity percent complete will not roll up (summary%) to WBS level, only for each activities.

 

kannan

arvin pura
User offline. Last seen 9 years 27 weeks ago. Offline
Joined: 17 Mar 2014
Posts: 8

Hi Gary,

I do the steps you advised. Still it did not show.

Thanks.

Arvin

arvin pura
User offline. Last seen 9 years 27 weeks ago. Offline
Joined: 17 Mar 2014
Posts: 8

Hi Gary,

thanks.

Arvin

Gary Whitehead
User offline. Last seen 5 years 15 weeks ago. Offline

1) Admin > Admin preferences > Earned Value. Ensure "techique for calculating performance % complete" is selected as "activty % complete"

2) Display the column "performance % complete". This will show in totals.

 

Cheers,