Please anyone can help me about ...how to get a report in P6 showing Number of activities done per month along the project duration ?
thnx
Activity Count Per Month
Featured Partner
Top Posters
Zainab El-Beialy
3 posts
Kamlesh Parmessur
4 posts
MR JUDE C ANYAEGBU
0 posts
GeoVe
0 posts
Ashkan Mohammadi
0 posts
Jeroen De Bauw
0 posts
Senior Planning Engineer
0 posts
Kristian Mcwilliams
1 posts
dagogo dan - jumbo
2 posts
Alex Lyaschenko
27 posts
My suggestions are just for a workarounds.
In continuation to my previous suggestion. Assign a unique resource inall actvities. Open resource profile window. Select the unique resource. Make use of the show activities per time period. Click on the period you wish to show the activities. There you will see what you requires.
Regards,
thnx for reply & help
but i wish i could get it by month ... by every month how many activities are done ?!
i think by enable time interval in histogram of resource usage profile and click on every single month i can get how many number of activities after doing ur way in steping activities :)
thanks again for help
Add a single step in all activities.
Use the filter to extract the activities you wish to count.
Show the column steps count.
There you can view the #s desired. Change the column name to activity count.