Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Planned Monthly and Weekly Progress

2 replies [Last post]
Albert Balogo
User offline. Last seen 10 years 5 weeks ago. Offline
Joined: 9 Jun 2008
Posts: 44

Greetings!

Hi Planners,

I extracted the Planned monthly and Weekly progress in P6, but the percentages does not match at every end of the month. Weekly percentage is beat higher compared to monthly. All settings have been applied accordingly,  e.g. unit of time, resource analysis, and timescale. Anybody can explain this problem.

 

Regards

Albert

Replies

Albert Balogo
User offline. Last seen 10 years 5 weeks ago. Offline
Joined: 9 Jun 2008
Posts: 44

Thanks Mike, I really appreciate your quick response.

Mike Testro
User offline. Last seen 36 weeks 1 day ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi Albert

There are 12 months and 52 weeks in a year - so the weekly progress will overlap the months end and show a lerger result.

Best regards

Mike Testro