Ship impact protection system

2 replies [Last post]
Sunil Babu
User offline. Last seen 5 years 12 weeks ago. Offline
Joined: 8 Nov 2010
Posts: 156

Dear all,

   I need some guidelines for doing a ship impact protection system project programme. The major

   activities includes construction of two berths and a fender system for the ship impact protection.

   What are the major concerns while planning a programme for this work, berth construction  includes

   piling works also.  Expecting your valuable view points,

   With Regards,

           Sunil.

Replies

Sunil Babu
User offline. Last seen 5 years 12 weeks ago. Offline
Joined: 8 Nov 2010
Posts: 156

Hi Mike,

Thanks a lot for your valuable reply. In case of SIPS piling method what productivity

rate are we following? ,Thanks in advance for your reply..

Best Regards,

Sunil.

Mike Testro
User offline. Last seen 33 weeks 9 hours ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi Sunil

Piling will probably be done from an ofshore barge.

If so then you have to consider:

State of the tide

Wave configuration

Weather - monsoon

Support and supply tenders

When piling is in progress the rest of the work can follow for the jetty deck and top beams.

After that you will have normal access.

Best regards

Mike Testro