Cathodic protection groundbed scheduel

1 reply [Last post]
Katalin Hovanyi
User offline. Last seen 10 years 3 weeks ago. Offline
Joined: 18 Apr 2003
Posts: 38
I need to estimate the manhour and duration for approximately 50 m deep 8" diameter groundbed.
I guessed:
2 days transport&drilling&piping 48 hours
3 days anod&backfilling&abouve ground installations 72 hours
Is it more or less correct or I need to calculete with different parameters? I hope somebody scheduled something similar and can give me some actual data.
Thanks
Katalin

Replies

Samer Zawaydeh
User offline. Last seen 5 years 20 weeks ago. Offline
Joined: 3 Aug 2008
Posts: 1664
Dear Katalin,

I would suggest that you contact a master driller in your company if you are on the Contractor side or your local soil investigation company if you are on the Owner side.

My guess is that the numbers that you are proposing are on the optimistic side.

Best Regards,

Samer