Can anyone help please?
 
I have saved the baseline and is using it to calculate Schedule % Complete.
Im using an updated schedule to calculate performance % Complete.
 
Now my understanding is that when your baseline date is in progress your schedule % Complete will show progress. Now my baseline date has passed and my schedule % complete doesnt show progress. All my other activities show except a few activities. I have tried resource & cost loaded schedules, I have tried changing the settings when calculating but it doesnt work.
 
Please any help will be appreciated.
Dear All,                  I what to know is there any internationally accepted standard for work quantity Vs manhour?For example 50cubic meter concreting needs this much manhour, like that? Please help......I want to know how resourses can be assigned in activities.
Hi Performance % is used for Earned Value C alculations, as such cost being a metric is normal,,but the Schedule % complete using cost for calculating %complete (Goup Totals) at summary levels is not the right method. At activity level the Schedule % complete is based on duration. A work around is to manually create a Planned (Schedule) Progress using update progress and viewing the Duration %complete, which summarizes and provides Group Totals using Durations.   RegardsShareef
This is strange as far as i remember there was a time when we never loaded resources or cost in our pragram still we have worked with schedule and performance percent complete.  I believe that their must be a way to get these two by using durations only.Waiting for other experts Regards
 
 
Schedule & Performance % complete are shown on Summary bars only if your programme is cost loaded. A quick work around is to assign the activity duration as a resource to the activities and give a value to the Price/Unit of the resource you have used.
 
Regards,
 
 
Nicos Pozatos.
 
Yes I Have tried all options.The Issue is that when I assign cost to the activities the I am Getting the Summary Of both Schedule & Performance % Complete.But Without Cost When I am using Just Duration % Complete,it is not Available.Anyone else Please advise
Raymund, Thanks, got it
Raymund,
 
Thanks, got it sorted yesterday.
 
I made a rookie mistake, didnt update my baseline. After the update all was good.
Stephan, Just assign the
Stephan,
Just assign the Baseline in the Primary Baseline. Do not assign on the Project Baseline.
Regards,
Can anyone help please? I
Can anyone help please?
 
I have saved the baseline and is using it to calculate Schedule % Complete.
Im using an updated schedule to calculate performance % Complete.
 
Now my understanding is that when your baseline date is in progress your schedule % Complete will show progress. Now my baseline date has passed and my schedule % complete doesnt show progress. All my other activities show except a few activities. I have tried resource & cost loaded schedules, I have tried changing the settings when calculating but it doesnt work.
 
Please any help will be appreciated.
Dear All, I
Dear All,                  I what to know is there any internationally accepted standard for work quantity Vs manhour?For example 50cubic meter concreting needs this much manhour, like that? Please help......I want to know how resourses can be assigned in activities.
Hi Performance % is used for
Hi Performance % is used for Earned Value C alculations, as such cost being a metric is normal,,but the Schedule % complete using cost for calculating %complete (Goup Totals) at summary levels is not the right method. At activity level the Schedule % complete is based on duration. A work around is to manually create a Planned (Schedule) Progress using update progress and viewing the Duration %complete, which summarizes and provides Group Totals using Durations.   RegardsShareef
This is strange as far as i
This is strange as far as i remember there was a time when we never loaded resources or cost in our pragram still we have worked with schedule and performance percent complete.  I believe that their must be a way to get these two by using durations only.Waiting for other experts Regards
Schedule & Performance %
 
 
Schedule & Performance % complete are shown on Summary bars only if your programme is cost loaded. A quick work around is to assign the activity duration as a resource to the activities and give a value to the Price/Unit of the resource you have used.
 
Regards,
 
 
Nicos Pozatos.
 
Yes I Have tried all
Yes I Have tried all options.The Issue is that when I assign cost to the activities the I am Getting the Summary Of both Schedule & Performance % Complete.But Without Cost When I am using Just Duration % Complete,it is not Available.Anyone else Please advise
Try: Go to Group and Sort and
Try:
Go to Group and Sort and check tick box 'show group totals'