Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Level 1 House Building Durations and Completion Rates

2 replies [Last post]
Tom Stephenson
User offline. Last seen 6 years 8 weeks ago. Offline
Joined: 11 Oct 2016
Posts: 3
Groups: None

Hello all,

I would welcome suggestions for approximate durations for the completion of residential units in the UK (South).

Briefly the units for delivery are:

  • 1 and 2 bedroom flats;
  • 2, 3 and 4 bedroom detached and semi-detached respectively; and
  • 1, 2 and 3 bedroom detached bungalows.

I have previously worked on the basis of 12 weeks 'fit out' per 2 bedroom flat with concrete frame, delivering four per week (in 'sets'), tested commissioned and signed off; with a two week lag between 'sets', adjusting accordingly for one or three bedroom units by +/- 1w. These will be low-rise (assumed 0-3 stories) but will that affect the output?

I would estimate a house of a traditional construction to be around 22-26 weeks in terrace, and perhaps closer to 30 weeks for detached units?? Based on the logic of 3w-5w substructure & drainage, 10w superstructure & envelope and maximum of 11w internal fit out per unit (externals completed in blocks/phases) with consecutive sequencing at this early stage. Please set me straight if that is absolute hot air!!

Also, I would expect that this could be accelerated using timber frame/modular construction.

Also appreciated would be some guidance on the infrastructure etc required for a large greenfield scheme (approx. 500 units in total) e.g. civils work, green space, street furniture etc. and associated duration estimates.

I am aware that with a scheme of this size, the sale of plots would affect the overall programme of the scheme i.e. while 500 units could be built in, say 5 years, this would not be the actual required build rate, however for the purposes of this exercise I am just trying to establish working time, as opposed to actual elapsed duration for the delivery of the entire scheme.

Any help or comments greatly appreciated, and thank you for taking the time to read this post.

Cheers,

Tom

Replies

Tom Stephenson
User offline. Last seen 6 years 8 weeks ago. Offline
Joined: 11 Oct 2016
Posts: 3
Groups: None

Mike,

Thank you.

There is very little information at this stage e.g. I have planning application info on just under 100 units, and unit types only for the remainder.

I have only recently started as an Assistant Planner, so while I could probably produce a detailed construction programme, to do so for a scheme of this size, with no information is beyond my capabilities at current - especially within the timeframes. It would probably take me weeks!

Is starting from detail and working to summary the only reliable method for establishing an early programme?

Kind regards,

Tom

Mike Testro
User offline. Last seen 35 weeks 5 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi Tom - Welcome to planning planet.

Stop guessing and do it properly with a level 4 bottom up programme using FS links.

If you have Asta PowerProject use the Line of Balance feature to create a Time/Distance programme to get the whole site on 1 A3 sheet.

Best regards

Mike Testro