Hey Guys,
I have a question about Level of Effort. I am using P6 v8.2.
I am trying to get the level of effort to update the % complete as the linked activities are updated but can't seem to get it to work. I have reviewed the forum for similar topics and have tried everything relevant that I found. Setting % complete type, relationship types (SF, SS, FF...).
I built a new simple project with a LOE and with 3 assigned activities. I have tried linking in different orders, setting % complete type to Physical, Units & Duration. No matter what I do the LOE % complete (or activity, units or any other % complete type) will not change as activities are updated. I also tried to create a start and finish mileston, linking the activities and the LOE back to those. Everything is manpower loaded with costs. What am I missing?
Thanks for feedback.