Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Activity usage spreadsheet shows planned value in Stop period

3 replies [Last post]
SM PUM
User offline. Last seen 10 years 39 weeks ago. Offline
Joined: 15 Nov 2011
Posts: 77
Groups: None

Hi All,

i have a project that has non working days calender.The work was planned to remain stopped in october and November.But when I see the Activity usage spreadsheet in the Above said month it is showing Planned value cost.Why it is not zero?

 

Regards

Replies

Raymund de Laza
User offline. Last seen 3 weeks 6 days ago. Offline
Joined: 22 Nov 2009
Posts: 762

Hi,

It seems that the schedule was earlier planned as contineous and later on you made the changes to apply the new calendar with non working days.

I suggest you to reset your planned dates by replacing the planned dates with the current dates.

 

Hope this will help.

Rafael Davila
User offline. Last seen 1 week 6 days ago. Offline
Joined: 1 Mar 2004
Posts: 5241

Note that even if your calendars are ok you can still apply lag to costs and resources in some software, not to mention Bucket Planning, you shall also take a look at this. I am not sure but believe there is a setting to block some of this behavior within P6.

If you are displaying costs not during the period they accrue but at the moment of payment it can be one example of a possibility. Say the activity is performed during work months but payment received during non working months modeled using resource/cost lag.

Nilkamal Parikh
User offline. Last seen 1 year 8 weeks ago. Offline
Joined: 13 Jul 2009
Posts: 31

Hi,

Check the calander for the all items. May be some of the items may have different calander. Check the default project calander and the calander for resources as well.

I hope this will resolve your issue.

Nilkamal