Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Resource usage spreadsheet

1 reply [Last post]
Mahmoud mohamed
User offline. Last seen 14 years 6 days ago. Offline
Joined: 15 Jun 2008
Posts: 4
Groups: None
Hi
In P6 the resource usage spreadsheet show me the resource’s quantities distributed within the activity duration – I need to show the data as percentage within the duration

Replies

Arnold Puy
User offline. Last seen 9 years 42 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147
Hi Mahmoud,

You can do this by using the spreadsheet option --> Calculate Average.

Example: Total qty of your manhour is 20,000 hrs. divide the total qty by 100 which is equals to 200.

Write the 200 in "Divide interval totals by" & under the "Unit of Measure" put the % symbol.

Try this exercise.

Arnold