Copying Only Resources to all activities

4 replies [Last post]
waheed mirza
User offline. Last seen 12 years 35 weeks ago. Offline
Joined: 24 Nov 2010
Posts: 10

Hi i had prepared a schedule with out assigning any resource to a project.now i need to assign as per project requirement.so i find little difficult to add resource to all activities.

my Question is can we add resources in one go to all activities  and later we can change value if needed.sothing like that rather adding resource by clicking each activity and assigning.

hope you got the question 

my email id: waheedmirza1@gmail.com

Replies

waheed mirza
User offline. Last seen 12 years 35 weeks ago. Offline
Joined: 24 Nov 2010
Posts: 10

Dear Vladimir Liberzon

i use Primevera 6.0 version...

waheed mirza
User offline. Last seen 12 years 35 weeks ago. Offline
Joined: 24 Nov 2010
Posts: 10

thanks Kannan for wonderfull reply

Kannan CP
User offline. Last seen 23 weeks 6 days ago. Offline
Joined: 12 Jun 2008
Posts: 290
Groups: None

Hi Waheed,

If you are using P6, then select the required activities in the schedule. After that right click the mouse and assign resource of your choice to the activities. It is the solution. In P3 go for a global change.

Kannan

Waheed,

please specify the software that you use.

It is easy in Spider Project but I expect that you use something else.

Best Regards,

Vladimir