It is only a 3 storey bldg so the equipments are not that big. A trolley system using basement ramp could be used to install and remove the equipments. Another option is to assymble the equipments at the basement ex. chiller if any.
It seemed to me that the difficulty in doing such scheme is that in this project, the superstructure foot print is even bigger than the substructure foot print.
These projects are fun, I was part of a project recently and we were able to complete 6700m2 building (6 stories) with 18meter excavation in 6 months ($2 Million).
We have around 70 people at site working 20 hours a day with the necessary materials and equipment to complete the job. 3 Project Managers and steady finance.
with the above, the cycle could be 7 days/floor which gives us 42 days from B2 to RD but say 2 months for learning curve,etc.
As what Mike said, it is indeed a simple structure. I would prefer to have the shortest construction duration to significantly reduce the prelims cost.
1.Preparation and approval of priority shop drawings, bar bending schedules and delivery of first batch of rebar = 2 months from NTP
2. 1 month excavation works including final trimming to start 1 month from NTP
3.2 weeks blinding works (assuming raft foundation no piles) FS no. 2
4.Construct raft foundation 1 month SS no. 3 log 1 wk
5.Construct B2-B1 Columns and Retaining Walls 1 month SS no. 4 log 2 wks
6.Construct B1 Slabs and Beams 1 month SS 2 wks no. 5
7.Construct B1-GF Columns and Retaining Wall 1 month SS 2 wks no. 6
8.Construct GF Slabs and Beams 1 month SS 2 wks no. 7
9.The above shows total duration 4 months
10.L1 to Roof Deck= 2 months.
11.Total Civil/Structural Works duration is 6 months from NTP
12.Plumbing and Electrical SS no. 4 for 8 months
13.Mechanical and Fire Protection FS no. 6 for 6 months
14.Architectural Works 7 months FS no. no. 6 for 6 months
15.External Finishing Works and Landscaping 4 months FS 10
16.Total Project Duration is 9 months
As the duration becomes shorter, the prelims/overhead costs also becomes cheaper.
Mike, as I read your reply less than an hour ago, your comments regarding dangerous practice of a planning engineer is very much appreciated. However, maybe plenty or few members like me are excited to read what others have in their minds for this topic. And as the information flows freely I mean the replies, we could decide which information is likely to caught our attention or not.
My analysis was excluding piling works and starting from pile chiping.....and the reasons i didnt include the roof was that i wasnt critical activity for starting finishing works......
First one for foundation system : whether is piles with shoring works or whether is normal foundation , but whereas u have basement that mean shoring system will be applied and usually such system is required 6 months considering the factors which are mentioned by Samir .
And other stage for:
sub-structure : 3-4 months .
Super-structure : 2months .
Roof system :1 month.
Finishing with external packages 4 months since your building is offices.
I like what Haresh has provided. But you need to keep in mind that you have productivity factors, soil conditions, environmental factors, unforseen conditions and most important, it depends on the Contractors team that is going to be complete the project.
18-24 months is a good range. The choice depends on the client requirement as well. If you push the time, then the Contractors will increase the cost because they have to bring in more resources. So I suggest that you call up few contractor in your region and see what estimates they give you.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Hi Mike,
Your right, top-down is not a viable option.
It is only a 3 storey bldg so the equipments are not that big. A trolley system using basement ramp could be used to install and remove the equipments. Another option is to assymble the equipments at the basement ex. chiller if any.
regards,
arman
Hi Armando
If there is no external access to the basement level 0 then obviously top down construction is not a viable option.
If the M&E plant is in the basement then check how they are going to get it in - and out again in 15 years time.
Best regards
Mike Testro
Hi Mike,
You mean top-down substructure construction?
It seemed to me that the difficulty in doing such scheme is that in this project, the superstructure foot print is even bigger than the substructure foot print.
regards,
arman
Dear Mike,
These projects are fun, I was part of a project recently and we were able to complete 6700m2 building (6 stories) with 18meter excavation in 6 months ($2 Million).
We have around 70 people at site working 20 hours a day with the necessary materials and equipment to complete the job. 3 Project Managers and steady finance.
With kind regards,
Samer
Hi Armando
If you can spring the columns from the pile caps or the raft you can work in level 0 as soon as level 1 is de-propped.
This allows drains and services and the basement slab and lift pit to be carried out concurrent with the structure.
This should take off 4 weeks.
Best regards
Mike Testro
Dear armando,
As long as you can secure the resources to site, I agree with you.
With kind regards,
Samer
Hi Samer,
I would use the following:
1 floor set of table forms
2 floor sets of back props
3 mobile cranes for erection (no tower crane)
with the above, the cycle could be 7 days/floor which gives us 42 days from B2 to RD but say 2 months for learning curve,etc.
As what Mike said, it is indeed a simple structure. I would prefer to have the shortest construction duration to significantly reduce the prelims cost.
regards,
arman
Dear armando,
That is very optimistic figure. You need to identify the resources with that.
With kind regards,
Samer
Guys, I would say...
1.Preparation and approval of priority shop drawings, bar bending schedules and delivery of first batch of rebar = 2 months from NTP
2. 1 month excavation works including final trimming to start 1 month from NTP
3.2 weeks blinding works (assuming raft foundation no piles) FS no. 2
4.Construct raft foundation 1 month SS no. 3 log 1 wk
5.Construct B2-B1 Columns and Retaining Walls 1 month SS no. 4 log 2 wks
6.Construct B1 Slabs and Beams 1 month SS 2 wks no. 5
7.Construct B1-GF Columns and Retaining Wall 1 month SS 2 wks no. 6
8.Construct GF Slabs and Beams 1 month SS 2 wks no. 7
9.The above shows total duration 4 months
10.L1 to Roof Deck= 2 months.
11.Total Civil/Structural Works duration is 6 months from NTP
12.Plumbing and Electrical SS no. 4 for 8 months
13.Mechanical and Fire Protection FS no. 6 for 6 months
14.Architectural Works 7 months FS no. no. 6 for 6 months
15.External Finishing Works and Landscaping 4 months FS 10
16.Total Project Duration is 9 months
As the duration becomes shorter, the prelims/overhead costs also becomes cheaper.
Mike, as I read your reply less than an hour ago, your comments regarding dangerous practice of a planning engineer is very much appreciated. However, maybe plenty or few members like me are excited to read what others have in their minds for this topic. And as the information flows freely I mean the replies, we could decide which information is likely to caught our attention or not.
Best regards,
Arman
Hi to All replies
When you list periods in weeks for various stages you are just guessing at top down durations - which is a dangerous practice.
You will not know the true duration until you have done a detailed bottom up critical path programme.
As I have said before in this forum the task should take little more that a day or two for a skilled planner and less than half a day for me.
Best regards
Mike Testro
Yes Mai t,
My analysis was excluding piling works and starting from pile chiping.....and the reasons i didnt include the roof was that i wasnt critical activity for starting finishing works......
regards
Haresh
Hi Haresh:
Your report has to show 2 work stages :
First one for foundation system : whether is piles with shoring works or whether is normal foundation , but whereas u have basement that mean shoring system will be applied and usually such system is required 6 months considering the factors which are mentioned by Samir .
And other stage for:
sub-structure : 3-4 months .
Super-structure : 2months .
Roof system :1 month.
Finishing with external packages 4 months since your building is offices.
The total will be; 15-16 months.
Regards .
Mai t.
Hi Ashutosh
2 basements and 3 storeys above - simple structure.
Why not take a day out and set up a simple bottom up programme to see how long it will take to build.
Best regards
Mike Testro.
Dear Ashutosh,
I like what Haresh has provided. But you need to keep in mind that you have productivity factors, soil conditions, environmental factors, unforseen conditions and most important, it depends on the Contractors team that is going to be complete the project.
18-24 months is a good range. The choice depends on the client requirement as well. If you push the time, then the Contractors will increase the cost because they have to bring in more resources. So I suggest that you call up few contractor in your region and see what estimates they give you.
With kind regards,
Samer
Total Duration reqd.
1)Foundation works - 80 days.
2) Basement- 2 - 45 days.
3) Basement - 1 - 30 days.
4) 3 Floors - 3X18 - 54 days.
5) Finishing works
after completion of - 210 days. (7 Months for office building)
Structure
Total reqd duration is = 420 days.i.e. 14 to 15 months, if the location is in Middleeast...