Possibly part of your project technical specifications is the general requirements that indicate also the project scheduling specifications. This document includes the administrative and procedural requirement of the Critical Path Method of scheduling and reporting progress of the work.
Review also contractual documents (COC, etc) to verify NTP date, Contract Milestones, schedule submission date, mobilization date, contract duration, NOC/permitting requirements, etc.
Links given by Rodel are very useful in reviewing both the baseline and updates.
If you are new to scheduling then your boss cannot expect that you can go into the details and comment upon the quality and the intricate details of the schedule....but
As a start point see if you can do some of these
1. Is the schedule as per Clause 14 condtitions.
2. Conduct a detailed analysis of the tasks that are related to the owners and consultants deliverables and obligations.
3. Check out all the constriants and question their existence.
4. Resource histograms and question the productivtiy factor used.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Rabbani,
Clause 14 in FIDIC 1987 edition, and Clause 8 (8.3 Programme)in FIDIC 1999 which is widely used nowadays especially in Middle East region.
Best regards,
R. Catalan
Dear Raddani,
First you have to be sure what version of FIDIC you have in your contract.
The latest version of FIDIC: There is no more clause 14 as it ralates to planning.
Thank you,
Scarlett
Dear Raddani,
Possibly part of your project technical specifications is the general requirements that indicate also the project scheduling specifications. This document includes the administrative and procedural requirement of the Critical Path Method of scheduling and reporting progress of the work.
Review also contractual documents (COC, etc) to verify NTP date, Contract Milestones, schedule submission date, mobilization date, contract duration, NOC/permitting requirements, etc.
Links given by Rodel are very useful in reviewing both the baseline and updates.
Best regards,
R. Catalan
Raddani,
If you are new to scheduling then your boss cannot expect that you can go into the details and comment upon the quality and the intricate details of the schedule....but
As a start point see if you can do some of these
1. Is the schedule as per Clause 14 condtitions.
2. Conduct a detailed analysis of the tasks that are related to the owners and consultants deliverables and obligations.
3. Check out all the constriants and question their existence.
4. Resource histograms and question the productivtiy factor used.
5. Check the TF column.
6. Float of the critcal path.
7. How many near critical paths and why.
Thanks
R
Dear Raddani,
You are most welcomed Read the Conditions of Contract and ask about everything you do not understand.
Face-to-Face is very important, so you must know your construction team and what they are doing on a daily basis.
With kind regards,
Samer
Dear Seniors,
Thanks a lot for your advise and guidance. Hopefully I will learn more with my efforts and PP seniors guidance.
Regards,
Rabbani
Hi Rabani
You say that you are new to planning - but are you new to construction also - if so you are going to have a very hard time of it.
Your use of Clause 14 indicates a FIDIC form of contract - hence a civils type programme.
First follow Samers advice and then check for a few tricks that contractors use to bamboozle the Engineer
1. Artificila contraints - they should all be removed except for the first task.
2. Calendars and work patterns - do the work hours reflect the actual.
3. How many links are SS / FF with lead lags - there should be none.
4. Is there a clear critical path - if not why not - and if there is more than one critical path it has been rigged.
5. How many tasks have no outgoing links - there should be at least one.
6. Are the early tasks a bit shorter than the later ones - if so the programme has been set up for an early delay claim.
Best regards
Mike Testro
Hi Rabbani,
Below link are some guide for checking Schedule and Baseline.
Checks and Balances: Baseline Schedule Review
Practical Baseline Schedule Checking
Dear Rabbani,
No one can answer this question except you. You need to open the Condition of Contract and read Clause 14.
The elements that you need to check, in general, are the following:
1.Schedule is complete and contains all the Contract Documents requirements.
2. Method Statement is logical.
3. Resources and durations.
4. Relationships.
5. Schedule development does not have any errors and the duration is meeting contract requirement.
With kind regards,
Samer