Clause 14 Program

2 replies [Last post]
Tanveer Ahmad Niazi
User offline. Last seen 6 years 47 weeks ago. Offline
Joined: 15 Dec 2005
Posts: 151
Groups: GPC Qatar

Hi planners,

Why the Program of Work (construction schedule) is called "Clause 14 Program" while this is not clause 14, its clause 8.3. Also Recovery program is known as clause 14.2

Cheers - Tanveer

Replies

Daniel Limson
User offline. Last seen 5 years 30 weeks ago. Offline
Joined: 13 Oct 2001
Posts: 318
Groups: None

In Europe and Middle East Countries, where Fidic Contracts are widely used, they normally refer to Clause 14 when it comes to programme issues and programme requirements, However, this is not applicable to East Asia or USA.

regards,

Daniel

Ferdinand U.
User offline. Last seen 7 years 24 weeks ago. Offline
Joined: 19 Jul 2007
Posts: 142

Originally came from old FIDIC '87 and reprinted 92, Programme related at Clause 14

Now,from FIDIC '99, Programme clause changed to Clause 8

but most contracts still adapt the 87/92 COC