clause14 and baseline program

1 reply [Last post]
Bysani Balaji
User offline. Last seen 16 years 34 weeks ago. Offline
Joined: 14 Aug 2007
Posts: 6
Groups: None
Hi Iam balaji working as planning engineer for Palm Jumeirah monorail station M&E works.
can any one help me in understanding wat is the clear difference between clause 14 and baseline program.

Replies

ashraf alawady
User offline. Last seen 9 years 42 weeks ago. Offline
Joined: 27 Aug 2006
Posts: 320
Groups: None
clause 14 in the general condition of contract is specifing the contractor responsibilties to submit a work program within 28 days from issuing the letter of acceptance from the client to the contractor.

clase 14 is divided into 4 sub clauses(14.1,14.2,14.3 and 14.4)
clause 14.1 is discripe the program of work to be submitted in the begeining of the project not later than 28 days after the date of letter of acceptance and after reviewing and approval of such program by the engineer/client this will be the apprved base line program.
clause 14.2 is discripe the coditions and requirements to submit revised program of work if at any time appear to the engineer that the actual progress of the works does not conform to the program to which consent has been given under sub-clause 14.1