Actual Labor units

No replies
Susan Young
User offline. Last seen 12 years 11 weeks ago. Offline
Joined: 3 Mar 2003
Posts: 35
Groups: None
Dear All,

I have loaded my schedule with Resources (labor). I guess P6 calculates Actual units complete based on ’Duration %’.

Any Ideas how I can generate the actual units based on ’Physical %’ ?

Sue