Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Engg:Drawings -Resubmit/Approval

3 replies [Last post]
Shah. HB
User offline. Last seen 49 weeks 3 days ago. Offline
Joined: 25 Nov 2008
Posts: 773
Hi to all

In detailed programme how to consider the contingency of material resubmission and approval of the same further is be considered?

Regards
Shahul

Replies

Safak Vural
User offline. Last seen 4 years 23 weeks ago. Offline
Joined: 12 May 2008
Posts: 117
Dear Shahul,

Please consider that some successor deliverables activity can start without waiting approval of predecessor one.

Ex: P&ID’s shall be a pred. of Isometrics but you will not wait for P&ID’s approval to start isometrics. You can revize IFC documents if necessary.

Regards,

Safak



Shah. HB
User offline. Last seen 49 weeks 3 days ago. Offline
Joined: 25 Nov 2008
Posts: 773
Many thanks samer
Samer Zawaydeh
User offline. Last seen 5 years 38 weeks ago. Offline
Joined: 3 Aug 2008
Posts: 1664
Dear Shahul,

It depends on your project and the type of material or shop drawings submittal.

You need to determine that during the early meetings with all parties at the start of the project.

On average you need to give 1.5 cycle time for resubmission. Usually the review period is between 1-2 weeks.

Your contractor should not be a wise guy and provide you will all the submittals to see at the same time with a review period between 1-2 weeks. This should be planned clearly depending on the stage of the project.

Plenty of ideas, but the best thing a team can do is to agree on a course of action at the start of the project.

With kind regards,

Samer