Planners,
I’m using P5 and I’m trying to plot out our (architectural)Labour Resources against our projects in a manner that would allow us to, at a glance, see who’s doing what until when and when they are freed up to move to other projects. This would be updated each month as the projects progress. I’ve tried a couple of options - putting in the project as a WBS with the various stages (Concept Design, Preliminary Design, Detail Design etc) as activities with the staff member(s) assigned as a resource to each activity (stage of work). Now I’m trying it ’the other way around’ by making the project the WBS, with each staff member as an activity underneath, giving them a duration (time committed to the project), but neither of these quite addresses our needs.
We want to be able to have an overview of our labour resource allocation.
Any ideas?
Thanks
Regards
Ian Perrins
Replies