Numerous Amount of Positive Float

3 replies [Last post]
Leonard Mon
User offline. Last seen 15 years 39 weeks ago. Offline
Joined: 28 Sep 2007
Posts: 21
Groups: None
Hi To All,

I need your valuable input regarding the below:

A particular activity (finish of survey work) in the Baseline CPM-PS has an EF on 21 Nov. 2007 with a total float of 42. However, in the Updated Current CPM-PS, such activity appears to have an EF on 21 feb. 2008 with a total float of 840 days.

I suspect that the updated Current CPM-PS portrays an unrealistic amount of Positive Float.

Is there something wrong about it? Kindly advise me how to make the necesary adjustment or to correct it.

Pls. note that we are using P3 Primavera.

Your reply is highly appreciated.
Best regards.
leonard

Replies

Leonard Mon
User offline. Last seen 15 years 39 weeks ago. Offline
Joined: 28 Sep 2007
Posts: 21
Groups: None
Hi James & Rav, thank you for your respective input.
I’ll do the checking now.

Highly appreciated.
best regards.

leonard
James Barnes
User offline. Last seen 1 year 36 weeks ago. Offline
Joined: 6 Sep 2007
Posts: 243
Raviraj is right. Also, check that links to successor activities have not been deleted or that those activities have actually started without the survey having been finished.

It’s possible that the groundworks were logically linked in the baseline to start after the survey was 100% completed, for example, but that in the event they were able to start while the survey work was ongoing, either by reorganisation of the works or because the logical link was an oversimplification to start with. In this event it may be that there is no longer any successor activity contingent on the completion of the survey and the Float would extend to the end of the project itself. It should then be logically tied back into the activities that are still contingent on it
A D
User offline. Last seen 4 years 3 weeks ago. Offline
Joined: 20 May 2007
Posts: 1027
Just check teh end date of both the projects. Plz also check weather there any mandatory constrainst in the baseline program or not?

if end date has moved considerably, then TF is also going to get changed.

Cheers,

Ravi