Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

baseline update progress

5 replies [Last post]
Lorenzo Tolentino
User offline. Last seen 3 years 37 weeks ago. Offline
Joined: 14 May 2007
Posts: 12
Groups: None
Greetings!

pls give me some idea why is it whenever i update progress, CTRL+F9, my baseline schedule i get negative floats on some activities? i supposed it shouldn’t be that way since this is an update progress of the baseline schedule and not updating the current sched...kindly give me some idea on this matter...what causes the negative floats of the above? thanks a lot and i wud aprc8 much ur help!!!

Replies

A D
User offline. Last seen 4 years 6 weeks ago. Offline
Joined: 20 May 2007
Posts: 1027
Or otherwise, there must be an imposed finish date for the project. (MUST FINISH BY)

This will generate negative float. Check this too..
armando moriles
User offline. Last seen 13 years 43 weeks ago. Offline
Joined: 2 Feb 2003
Posts: 66
Groups: None
Lorenzo,

Try to check if you have constraints applied on those activities that generate negative floats...

With regards to baseline updating, I agree with Anoon...

Regards,

Arman
Anoon Iimos
User offline. Last seen 2 years 49 weeks ago. Offline
Joined: 22 Sep 2006
Posts: 1422
you don’t have to make multiple copies of the baseline, i suggest you study what a Data Date is...
Lorenzo Tolentino
User offline. Last seen 3 years 37 weeks ago. Offline
Joined: 14 May 2007
Posts: 12
Groups: None
thank you mr. anoon for your reply...however, how do i get the the planned progress of every activity for a certain period of time? what we usually do here is that i make a copy of the baseline schedule then i would run that copy, CTRL+F9, to get the planned progress...is there a better way? Tnx a lot...
Anoon Iimos
User offline. Last seen 2 years 49 weeks ago. Offline
Joined: 22 Sep 2006
Posts: 1422
i don’t understand why you’re doing it, in principle, you don’t have to update the Baseline, you update only the current schedule.

in updating baseline in order to get the planned progress, you don’t have to change anything, you update it perfectly as planned.