Filter: Recently changed against baseline (BL1)

2 replies [Last post]
Vic Noztua
User offline. Last seen 10 years 31 weeks ago. Offline
Joined: 11 Sep 2013
Posts: 14

Please need assistance in filtering baseline against my recent changes or vise versa:

If I want to filter out which activities has been recently changed or date moved against my latest BL just for double checking, which parameter/s I should use in my filter? The purpose is to know if there are some unwanted changes or moved dates not accordingly. 

Thanks! 

Replies

Vic Noztua
User offline. Last seen 10 years 31 weeks ago. Offline
Joined: 11 Sep 2013
Posts: 14

Many thanks GARY, it's working! And yes I use primavera:-)

Gary Whitehead
User offline. Last seen 5 years 17 weeks ago. Offline

Vic,

 

To see all activities that have a diferent start or end date to your BL1 use:

Variance -BL1 Project Start Date is not equal to 0

OR

Variance -BL1 Project Finish Date is not equal to 0

 

(Assuming you are using Primavera)

Cheers,

 

G