Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

S-Curve

3 replies [Last post]
Vinai Maurya
User offline. Last seen 15 years 40 weeks ago. Offline
Joined: 31 Aug 2006
Posts: 7
How to draw Engineering, Ordering, Tendering schedule Curve. What will be the basis for weightage value. How it will be calculated.


From
Vinai

Replies

Karim Mounir
User offline. Last seen 10 years 15 weeks ago. Offline
Joined: 5 Apr 2006
Posts: 314
Groups: None
Vinai,

u can define a resource called "activity days", this resource will be loaded into each activity, the budgeted qty. for this resource in each activity will be equal to the original duration of the activity.

Now after loading your activities with this resource, u can make a tabular or graphical report that shows the distribution of this resource in a certain WBS level (Engineering, Ordering, Tendering, ..), this will give u the planned s-curve (note that the weight of each stage will depend on the OD of the activities under this WBS level).

After updating your schedule u can make tabular or graphical report that shows u the actual units of each activity which u can use to make a simple s-curve that shows Actual units VS. Planned units (all in terms of activity days resource).

ashraf alawady
User offline. Last seen 10 years 8 weeks ago. Offline
Joined: 26 Aug 2006
Posts: 320
Groups: None
Hi,
S-Curve should reprsent the excepected cash flow and it has a curve shape.
The actual meaning of the S-curve that the excepected cash flow in the starting of any project will be very small starting from zero and increasing slowly for the starting peroid( approx. 20% of the total contract period)and it will be increased stongly reaching to the peak value within the meddel period of the project( the next 60% of the total duration) and in the final stage(last 20% of the contract duration),the excepected cash will be reduced to reach to the total value of the project(accommulativly).
Zhang Haixiang
User offline. Last seen 4 years 7 weeks ago. Offline
Joined: 14 Apr 2005
Posts: 250
Groups: None
IMO for ordering & tendering no need.
for engineer...