Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

S-Curve to Bar Chart

2 replies [Last post]
Alfon Lyndon Joson
User offline. Last seen 7 years 46 weeks ago. Offline
Joined: 28 Mar 2004
Posts: 35
Groups: None
How do you incorporate/show the progress curve to the schedule bar chart??

Replies

Rahmat Hidayat
User offline. Last seen 12 weeks 2 days ago. Offline
Joined: 30 Jul 2002
Posts: 82
In P3 you can utilize Graphic Reports, then select Resource & Cost, and choose format with Curve for Overlay.I think you can also try by copy-paste s-curve from Excel into Ms Project. In short, there are many ways to make overlays, it’s easy and simple.

Regards
Waseem Saber
User offline. Last seen 2 years 22 weeks ago. Offline
Joined: 1 Dec 2004
Posts: 63
Groups: None
hi,

this is a vague question and i am surprised that such a requirement is requested by anybody,anyway the requirment of the s-curve to show on the bar chart format will nullify the very usage of the bar chart, and therefore don;t be misinformed and work as per the ethics.

cheers {.....}

waseem saber