S-Curve to Bar Chart

R
Rahmat Hidayat 👤 Member for 23 years 10 months

In P3 you can utilize Graphic Reports, then select Resource & Cost, and choose format with Curve for Overlay.I think you can also try by copy-paste s-curve from Excel into Ms Project. In short, there are many ways to make overlays, it’s easy and simple.



Regards

W
Waseem Saber 👤 Member for 21 years 6 months

hi,



this is a vague question and i am surprised that such a requirement is requested by anybody,anyway the requirment of the s-curve to show on the bar chart format will nullify the very usage of the bar chart, and therefore don;t be misinformed and work as per the ethics.



cheers {.....}



waseem saber