Budgeted Manhours

B
Bernard Ertl 👤 Member for 23 years 8 months

For industrial plant turnaround maintenance projects, we expect the scope to change - sometimes dramatically. We code and track scope as original and add-on for post-project cost analysis. We track summary (physical) progress as the percent of total manhours complete against a statistical minimum attainment curve for the desired time span.



Bernard Ertl

ATC Professional Shutdown / Turnaround Management System

D
Daniel Limson 👤 Member for 24 years 9 months

If the additional manhours is a result of an additional scope thru change order or change directives then you treat it separate from the base scope. You can achieved this by making a separate code, in effect having a separate sub-total for your baseline and additional works.



On the other hand, if it is merely an additional manhours as a result of estimated manhours being wrong, then you simply revised your manhour estimates to incorporate the additional manhours.



Hope this helps.



Cheers,

Daniel

Featured Partner

Top Posters

Zine Eddine
2 posts
Alex Lyaschenko
27 posts
mxsiegel
0 posts
Mattvtek
0 posts
Gareth Evans
3 posts
PP Admin
3, 129 posts
Rajkamal Tangirala
5 posts
Rahul Kumar
1 posts
blake333_
0 posts
Jeamiell Ostrovsky
2 posts