Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Budgeted Manhours

3 replies [Last post]
Daniel Jeyaraj Be...
User offline. Last seen 15 years 24 weeks ago. Offline
Joined: 19 Jan 2004
Posts: 16
All,
I’m not sure if this question has been discussed before.

When additional manhours occurs as the project goes on, how do you benchmark it against the budgeted mhrs in the baseline programme? I mean how do you measure the progress as the parameters in both the programme is of different value (baseline vs current updated programme), and it will still change in future.

Thanks



Replies

Daniel Jeyaraj Be...
User offline. Last seen 15 years 24 weeks ago. Offline
Joined: 19 Jan 2004
Posts: 16
Thanks guys for the reply.
Bernard Ertl
User offline. Last seen 9 years 50 weeks ago. Offline
Joined: 20 Nov 2002
Posts: 757
For industrial plant turnaround maintenance projects, we expect the scope to change - sometimes dramatically. We code and track scope as original and add-on for post-project cost analysis. We track summary (physical) progress as the percent of total manhours complete against a statistical minimum attainment curve for the desired time span.

Bernard Ertl
ATC Professional Shutdown / Turnaround Management System
Daniel Limson
User offline. Last seen 5 years 18 weeks ago. Offline
Joined: 13 Oct 2001
Posts: 318
Groups: None
If the additional manhours is a result of an additional scope thru change order or change directives then you treat it separate from the base scope. You can achieved this by making a separate code, in effect having a separate sub-total for your baseline and additional works.

On the other hand, if it is merely an additional manhours as a result of estimated manhours being wrong, then you simply revised your manhour estimates to incorporate the additional manhours.

Hope this helps.

Cheers,
Daniel