Would everyone here use a 3/1 data date for February progress?

J
John Reeves 👤 Member for 13 years 1 month

Would everyone here use a 3/1 data date for February progress? (aside from some stated date like the 15th etc.) - this way it would match Feb. cost data etc., I always heard that the data date line was like 8am or whatever starting time.  I assume in theory that could be changed to 5pm or whatever ending time but I have never heard of anyone doing that.  

R
Rodel Marasigan 👤 Member for 19 years 7 months

The recommended and standard practice of data date is last working date and time of the reporting cycle.

Ex: Weekly cut-off = every Friday Cut-off at last working time say 5:00PM 

     Bi-weekly cut-off = alternate Friday Cut-off at last working time say 5:00PM

     Monthly cut-off = Last Friday of the Month at last working time say 5:00PM

     Shutdown per shift = Say at every 6:00PM 1st Shift and 6:00AM 2nd Shift

Forum Sponsor

Top Posters

JAGAN REDDY MUSUKU
0 posts
Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts