Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

What would cause P6 to NOT use the default units/time when assigning a resources?

2 replies [Last post]
Alex Garcia
User offline. Last seen 1 year 2 weeks ago. Offline
Joined: 21 Sep 2016
Posts: 9
Groups: None

When assigning resources, P6 isn't using the default units/time to populate the budgeted units.  For example, our resources are set to 8h/day.  So, when we assign a resource to an 8 day activity, the default budgeted units should be 64h, with 8h/day.  But, it's loading 264h @ 33h/day.  What would drive this, and how can it be fixed?

Replies

Rodel Marasigan
User offline. Last seen 11 weeks 7 hours ago. Offline
Joined: 25 Oct 2006
Posts: 1699

Assigning resources in P6 is calculated based on Resouce Calendar time period, resource default unit/time and activity type calendar time period. If activity type is Resource dependent then it will use resource calendar and if activity type is task dependent it will use task calendar.

I often see that the time period has always been neglected and forgot to change and match the calendar setting per day. This always the cause why the duration calculation is not correct including the resource assignment calculation.

Ex: 
1) Resource Calendar time period = 8hrs/day, calendar 16hr/day x 5 days/week
2) Resource Default Units/Time  = 16hrs/day
3) Task Caledar time period = 10hrs/day, calendar 8hrs/day x 5 days/week

Resource assignment calculation will be Resource units/ time divided by Resource Calendar time period multiple by Task Calendar time period = 16hrs / 8hrs x 10hrs = 20hrs/day (remaining unit/time)  x activity duration say 5 days = 100hrs

On your example it seems that the resource calendar time period is not matching the default unit/time (i.e 8h/day). Checked the resource calendar time period if it is also set 8hrs/day and matching default unit/time assigned to resources and also check the activity calendar time period if matching the calendar settings of 8hrs/day.

Zoltan Palffy
User offline. Last seen 20 weeks 3 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

double check the default units/time

manke sure that you durations are set to fixeded duration and units/time

david kelly
User offline. Last seen 6 weeks 5 days ago. Offline
Joined: 12 Feb 2016
Posts: 34
Groups: None

Eh, nothing? The only thing i can think of is the resource calendar?