Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Data date: you can use the 1st of month every month, does not matter if falls on Sundays etc correct?

3 replies [Last post]
John Reeves
User offline. Last seen 11 weeks 3 days ago. Offline
Joined: 10 May 2013
Posts: 343
Groups: None

Data date:  you can use the 1st of month every month, does not matter if falls on Sundays etc correct?

Replies

Santosh Bhat
User offline. Last seen 35 weeks 3 days ago. Offline
Joined: 15 Apr 2005
Posts: 381

John it's quite fesible if the contract specifies that the schedule must be updated on a certain day of the month (eg. 28th of each month) that this lands on a weekend. 

John Reeves
User offline. Last seen 11 weeks 3 days ago. Offline
Joined: 10 May 2013
Posts: 343
Groups: None

I am not sure why you would say but, if the activity does not have a Sunday and does not fall on a Sunday there is no issue.  I am just wondering if these is a Sat or Sun data date on a schedule with mainly 5 day calendars.  I cannot think of one.

Santosh Bhat
User offline. Last seen 35 weeks 3 days ago. Offline
Joined: 15 Apr 2005
Posts: 381

yes, but if your activity calendars have Sunday as a non-work day then any activity that would commence on the datadate will not fall on that Sunday.