Guys,
Very interesting. Rodel’s solution updates At Completion hours as well as Estimate at Completion hours, this means you lose some of the variances, but not ones I care about very much. It also sets Remaining Labour Hours to the same as Estimate to Complete Labour Hours, which I am not very comfortable with.
My issue with it is I am used to separate responsibilities for earned and expended progress. My solution means the update of expended hours does not require the authority to change % completes. This fits well with the security profiles of cost and planning I am used to. If there is only one person manually updating both, Rodel’s system will work much better than if the timesheet system is updating Actual hours under-the-hood. Automated timesheet updates are not authorised (yet!) to update Activity % completes.
Of course, some very bizarre results will happen if lots of timesheet hours are recorded ahead of Earned progress at the start of an activity. This is a familiar problem when calculating Estimate to Complete manhours, but Rodel’s system recalculates Remaining Manhours as well. If one person is updating all of the data into P6, and issues all reports, then the requirement for manual adjustment can be tracked fairly easily. My system was designed for 10-20k timesheet records a week, updated automatically
Budget 500 hours, Earned progress 5%, Timesheet hours 100 = 1900 hours remaining, which may be true, but it is more likely to be a function of the early stage of the job rather than linear liquidation of the manhours.
Rodel:
Update units % complete –
Save units % complete to a UDF
Update ‘Real’ actual hours
Reload saved units% complete
Update remaining durations
David:
Update Physical % complete
Run Global changes to recalculate RD and Remaining resources/units
Manually update remaining duration and remaining resources for those activities where Physical % complete does not calculate RD or RR the way we want
Timesheet hours can be updated any time, any number of times, by somebody else