Importing into P6 using Microsoft Excel

No replies
John Reeves
User offline. Last seen 9 weeks 1 day ago. Offline
Joined: 10 May 2013
Posts: 344
Groups: None

I have been using P6 a long time but only import actuals and changes using MS Excel occassionally.  I have forgotten the "little things", - it is not importanting all of the data - what are the common mistakes? - Do I have to put a U somewhere or include some account code or something, possibly some things cannot be updated?  I do not know what I am forgetting.

Santosh Bhat
User offline. Last seen 5 weeks 1 day ago. Offline
Joined: 15 Apr 2005
Posts: 381

Also remember, if you generate an XLS Export from P6, the columns marked with an (*) cannot be imported in.

Rodel Marasigan
User offline. Last seen 25 weeks 5 days ago. Offline
Joined: 25 Oct 2006
Posts: 1699

Basic Importing Note P6 using MS Excel

1) Any fields with * are calculated field and cannot be imported

2) There are 5 tables that can be updated using MS Excel such as:

a) Activity table (TASK)
b) Activity Relationships (TASKPRED)
c) Expenses (PROJCOST)
d) Resources (RSRC) - resource library
e) Resource Assignment (TASKRSRC)

 

Default columns per subject area   
ActivitiesActivity RelationshipsExpensesResourcesResource Assignments
Activity IDPredecessorActivity IDResource IDActivity ID
Activity StatusSuccessorExpense ItemResource NameActivity Status
WBS CodeRelationship TypeActivity StatusResource TypeResource ID
Activity NamePredecessor Activity StatusBudgeted/Planned CostUnit of MeasureRole ID
StartSuccessor Activity StatusActual CostRole IDCost Account ID
FinishPredecessor ProjectRemaining CostDefault Units / TimeResource Type
ResourcesSuccessor ProjectAt Completion Cost Price / Unit
 Predecessor WBS  Start
 Successor WBS  Finish
 Predecessor Activity Name   
 Successor Activity Name   
 Lag   
 Predecessor Primary Resource   
 Successor Primary Resource   

Note:

Italic text indicates that the column is required for importing and exporting. The column cannot be removed from the export template and must exist in the import file to import successfully.