Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Percentage Complete in Schedule - Overall

No replies
Jithin Kambhikanam
User offline. Last seen 8 weeks 5 days ago. Offline

Hi All,

 

Can we show the % complete in tthe schedule by WBS and so get the overall % complete of the Project.

We would be updating the activity % complete but can the WBS show the oerall % complete based on the activity pogress %.

A schedule which has Engineering - Measured in Manhours, Procurement - Measured in Cost, Construction - Measured in Manhours.

I do make the OVerall % Complete and indivigual WBS % complete in Excel.

Waiting for your input. 

 

Thanks

Jithin

John Reeves
User offline. Last seen 2 weeks 6 days ago. Offline
Joined: 10 May 2013
Posts: 343
Groups: None

Procurement measured in cost sounds odd, would all depend on the project though.

Rodel Marasigan
User offline. Last seen 3 days 23 hours ago. Offline
Joined: 25 Oct 2006
Posts: 1699

You can use performance % complete which is the activity % complete  based on the Percent Complete type.

depending on P6 version your using, below P6v17xx or P6v16xx Performance % Complete - labour units is not available and only cost driven so I recommend to micmic the budget hours by setting $1 = 1 hour for Engineering and Costruction so you can have Overall % complete per WBS and overall using Performance % complete.