Activity Percentage Complete vs Schedule Percentage Complete

I
Irfan Khan 👤 Member for 16 years 11 months

 I am working in a construction company and I prepared a cost loaded schedule but I am confused while updating of my schedule.

Schedule Status:         Duration Type = Fixed Duration & Units

                                % Complete Type = Physical

WBS Status:               I defined 4 phases

                                    1 = General Requirements (not cost Loaded)           

                                    2= Design Drawing (not cost Loaded)           

                                    3=Construction Phase (Cost Loaded)

                                    4=Project Close Out (not cost Loaded)

Problem: While updating the Percentage to activities which is under General Requirements or Design Drawing the band of WBS is not showing overall percentage of that WBS.

Inspite WBS of General Requirements or Design Drawing, Construction Phase is showing percentage on its bands & whenever I am giving percentage to Activities (in the column of Activity % Complete) 50% the Schedule % complete showing 100%.

  1. How these parameters are working please explain somebody?                    
  2. So can somebody tell me how to show percentage on band of these two WBS bands?   
  3. Which is the best way to update your schedule ?

Please reply somebody …..i ill be highly obliged

 

Thanks

Forum Sponsor

Top Posters

Peter Holroyd
51 posts
fridau
0 posts
Rahmat Hidayat
32 posts
pinoyplanner
1 posts
James Williams
74 posts
Saqib Ullah
1 posts
Luyanda Ndlumbini
2 posts
Jeff Waldrop
6 posts
Robert Roy
1 posts
Tony Wright
4 posts