Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Activity Percentage Complete vs Schedule Percentage Complete

1 reply [Last post]
Irfan Khan
User offline. Last seen 27 weeks 5 days ago. Offline
Joined: 19 Jul 2009
Posts: 138

 I am working in a construction company and I prepared a cost loaded schedule but I am confused while updating of my schedule.

Schedule Status:         Duration Type = Fixed Duration & Units

                                % Complete Type = Physical

WBS Status:               I defined 4 phases

                                    1 = General Requirements (not cost Loaded)           

                                    2= Design Drawing (not cost Loaded)           

                                    3=Construction Phase (Cost Loaded)

                                    4=Project Close Out (not cost Loaded)

Problem: While updating the Percentage to activities which is under General Requirements or Design Drawing the band of WBS is not showing overall percentage of that WBS.

Inspite WBS of General Requirements or Design Drawing, Construction Phase is showing percentage on its bands & whenever I am giving percentage to Activities (in the column of Activity % Complete) 50% the Schedule % complete showing 100%.

  1. How these parameters are working please explain somebody?                    
  2. So can somebody tell me how to show percentage on band of these two WBS bands?   
  3. Which is the best way to update your schedule ?

Please reply somebody …..i ill be highly obliged

 

Thanks

Replies

Domingo Bonaobra
User offline. Last seen 1 year 15 weeks ago. Offline

Hi Irfan,

This had been discussed in previous thread. Please follow this links, this might helps you..

http://www.planningplanet.com/forums/primavera-version-pm5-pm6/419588/schedule-complete 

Regards

Doming