Here is what I think it has to do with - the default setting for each project is "shared". I change it to exclusive it to exclusive and open it. But when I close and look at it again all the files default back to shared. My guess is that P6 is not letting you make a shared file a baseline. I have no way to keep it exclusive - is this a citrix thing? is this a admin thing. I have used P6 for 30 thirty at 25 different places but am new on this setup. I am not an admin person. Any ideas?
Citrix implemented p6 - I can't assign another project as a baseline & can't figure out why - any ideas?
Forum Sponsor
Top Posters
David Smith
4 posts
Peter Holroyd
51 posts
fridau
0 posts
Rahmat Hidayat
32 posts
pinoyplanner
1 posts
James Williams
74 posts
Saqib Ullah
1 posts
Luyanda Ndlumbini
2 posts
Jeff Waldrop
6 posts
Robert Roy
1 posts
to turn off auto calc in P6
go to tools schedule
then options
then in the top part 4th item down uncheck the box that says scheduel automatically when a change affects dates
also if you are using a citrix I would recommend preseing the F10 function key from time to time this will save your work
it is the same as selecting file Commit Changes
OK, I answered my own question there - so how about this one - what can you turn off in P6 to make it run faster? I know you should turn off the line drawing. I know in p3, excel, etc you can turn off the auto calc. I think it is default off in P6 - I don't know even how turn on autocalc if it has it. But I am working in citrix and constantly seeing the hour glass just to move row to row. Its not the internet, just looking to make sure there is not a calc of nothing going on. ie no resources - but it might be calcing in case there are or something.
OK, I answered my own question there - so how about this one - what can you turn off in P6 to make it run faster? I know you should turn off the line drawing. I know in p3, excel, etc you can turn off the auto calc. I think it is default off in P6 - I don't know even how turn on autocalc if it has it. But I am working in citrix and constantly seeing the hour glass just to move row to row. Its not the internet, just looking to make sure there is not a calc of nothing going on. ie no resources - but it might be calcing in case there are or something.
OK, this one is on me. For whatever reason I was not used to seeing the "maintain" choices rolled up to the top EPS element, once I clicked on that it opened up and the choices were there. I think I was quick to think it was the system due admin and citrix issues in the past when on a new system.