Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

P6 Professional R19.12 Import Resource Assignment from Excel

3 replies [Last post]
Steven Montgomery
User offline. Last seen 9 weeks 1 day ago. Offline
Joined: 31 Mar 2017
Posts: 26
Groups: None

My ASST SCN has a payrate of $39.62 as diplayed below.

7933
figx_0.jpg

I export the below schedule with the respective activity resource assignments.

7934
figx_4.jpg

The exported TASKRSRC worksheet displays as below.

7935
figx_2.jpg

I import this Excel to a schedule with no resource assignments.

7936
figx_3.jpg

When the Resources and Resource Assignments are imported I get the below.

7938
figx_1.jpg

Why does the Price/Unit import as $1.00/h^?

And I cannot manually change the Price/Unit of Assistant Scientist/A.

The only way to correct the Price/Unit is to delete the resource assignment and re-assign the resource. But this defeats the purpose of importing the Resource Assignmnent from Excel.

Any thoughts?

 

--Steve

Replies

Steven Montgomery
User offline. Last seen 9 weeks 1 day ago. Offline
Joined: 31 Mar 2017
Posts: 26
Groups: None

Rodel,

Okay, thanks, tools | recalculate assignment costs worked.

 

--Steve

David Kelly
User offline. Last seen 2 years 41 weeks ago. Offline
Joined: 19 Oct 2004
Posts: 630
Steve, You need to check the default rate that new resource allocations use, which is in the 'Resources' tab at the project level. If you do not specify which rate to use on the Export/Import process (you can) , that is the one it will use.
Rodel Marasigan
User offline. Last seen 17 weeks 6 days ago. Offline
Joined: 25 Oct 2006
Posts: 1699

Hi Steve,

I already explained to you why you are getting Price/Unit $1.00/h^. If you have the price/unit setup and after the import still showing Price/Unit = $1.00/h^ but having the correct amount, it means that you have not refresh the schedule assignment cost. To refresh, On the menu under Tools, select "Recalculate Assignment Cost" and a window pop-up will show as per sample below.

Recalculate-Assignment-Cost

Click Recalculate and the assignment cost will be refresh.