Day Rate for Resources

2 replies [Last post]
Krishna Chattoo
User offline. Last seen 5 years 9 weeks ago. Offline
Joined: 20 Jun 2019
Posts: 2
Groups: None

Is there a way to enter a day rate rather than an hourly rate in Primavera?

Replies

Zoltan Palffy
User offline. Last seen 21 weeks 14 hours ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

in the resource the default units/time is day

Raymund de Laza
User offline. Last seen 8 weeks 4 days ago. Offline
Joined: 23 Nov 2009
Posts: 762

Set the Unit of Time in Day for Unit Format and Duration Format in the User Preferences under Time Units Tab