LoE budgeted units not matching activity calendar

2 replies [Last post]
Dan Pitts
User offline. Last seen 4 years 34 weeks ago. Offline
Joined: 23 Nov 2011
Posts: 3
Groups: None

I have a role assigned to a LoE (fixed duration & units/time) which has a standard 5 day calandar.

Budgeted units / time is 100% and the total budgeted units in the resource assignments window match the activity duration. Planned dates match forecasted.

 

The issue is that in the resource assignments spreadsheet it is showing 25 units in June 2019 where the calendar only has 20 working days. Why are the budgeted units not aligned to the activities calendar?

Replies

Zoltan Palffy
User offline. Last seen 14 weeks 4 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

if you assign a budget to a LOE activity type you MUST assign a resource CURE or the units will all stuck up on the data date.

Dan Pitts
User offline. Last seen 4 years 34 weeks ago. Offline
Joined: 23 Nov 2011
Posts: 3
Groups: None

Hmm... have just restarted Primavera and all appears to be displaying as expected in the resource spreadsheet. Weird!